Legislation Details

File #: 24-399    Version: 1 Name:
Type: Informational Report Status: Agenda Ready
File created: 11/27/2024 In control: City Council, Financing Authority, and Successor Agency to the Claremont Redevelopment Agency
On agenda: 12/10/2024 Final action:
Title: AWARD OF CONTRACT TO PINEDA GENERAL CONSTRUCTION, INC. FOR THE BLAISDELL COMMUNITY CENTER KITCHEN REMODEL PROJECT (FUNDING SOURCE: GENERAL CAPITAL PROJECTS FUND)

TO:                     ADAM PIRRIE, CITY MANAGER

 

FROM:                     JEREMY SWAN, COMMUNITY SERVICES DIRECTOR

 

DATE:                     DECEMBER 10, 2024

Reviewed by:

City Manager: AP

                     

SUBJECT:

 

Title

AWARD OF CONTRACT TO PINEDA GENERAL CONSTRUCTION, INC. FOR THE BLAISDELL COMMUNITY CENTER KITCHEN REMODEL PROJECT (FUNDING SOURCE: GENERAL CAPITAL PROJECTS FUND)

Body                     

 

SUMMARY

 

The Blaisdell Community Center kitchen is in need of a remodel due to its age and current demand. The site has provided meal service to seniors for the past forty years and is outdated. The small kitchen was designed to serve meals to approximately thirty people daily, but now serves more than fifty people daily. Demand for lunch service is increasing; however, the facility is struggling to accommodate the need due to aging infrastructure and overcrowding.

 

In April 2024, the City solicited bids for the Blaisdell Community Center Kitchen Remodel Project. At the end of the bid period, no bids were received. In August 2024, staff directly contacted three contractors for quotes, two of which were non-responsive. OTL Builders, Inc. submitted a proposal of $69,300 to complete the project. Prior to signing the contract, OTL Builders, Inc. provided the City with a revised scope of work and declined the original scope of work to which they had agreed. In October 2024, the City again solicited bids for the project. At the end of the bid period, two bids were received for $109,595 and $127,700.

 

RECOMMENDATION

 

Recommended Action

Staff recommends the City Council:

A.                     Award a contract to Pineda General Construction, Inc. in the amount of $109,595 for the Blaisdell Community Center Kitchen Remodel Project and authorize a ten percent contingency in the amount of $10,959, for a total amount not to exceed $120,554, and authorize the City Manager to execute the agreement;

B.                     Authorize the City Manager to enter into an agreement with Lotus Construction Group in the amount of $7,000 for project management services;

C.                     Appropriate $127,554 from the General Capital Projects Fund to fully fund the Blaisdell Community Center Kitchen Remodel Project; and

D.                     Authorize acceptance of $127,554 from the Claremont Senior Foundation, Inc. to reimburse the City for the total cost of the project.

Body

 

ALTERNATIVES TO RECOMMENDATION

 

In addition to the recommendation, there are the following alternatives:

 

A.                     Request additional information from staff.

B.                     Reject all bids and direct staff to rebid the project.

 

FINANCIAL REVIEW

 

The proposed cost of the Blaisdell Community Center Kitchen Remodel Project is $109,595, plus a ten percent contingency of $10,959, for a total cost of $120,554. The cost for Lotus Construction to provide construction management services on the project is $7,000. The total project cost is $127,554, which will be funded using the General Capital Projects Fund. Once the project is complete, the Claremont Senior Foundation, Inc. will reimburse the City for the full cost of the project.

 

The staff cost to prepare this report and administer this project is estimated at $4,946 and is included in the operating budget of the Community Services Department.

 

ANALYSIS

 

The Blaisdell Community Center serves as one of the Claremont Senior Program’s two lunch sites, providing a hot meal for seniors and a friendly atmosphere that encourages socialization, fun, and ways to participate in the full array of programs and services offered by the Claremont Senior Program. However, after forty years of nonstop service as a nutrition site for seniors, the Blaisdell Community Center’s kitchen is not able to keep up with the demands placed on it as a bustling congregate meal site, a source for social service referrals, and a festive special event venue. The kitchen is cramped and outdated, making it challenging for staff and volunteers to hold daily meal deliveries at a safe temperature until time for service. The electrical system is outdated and unable to meet the needs of current appliances and programs. Additionally, the Blaisdell site lacks the dishwasher and plated service available at the Joslyn Center, the other location providing senior meal service.

 

In response to this need, the Claremont Senior Foundation, Inc. (CSF) launched a multi-year fundraising campaign in 2019 to revamp the kitchen. The CSF is a non-profit organization that has existed since 2006 solely to serve as a steward for funds that benefit the Senior Program. Thanks to the CSF’s leadership, large grants and many gifts from community donors resulted in exceeding the goal to support this initiative.

 

Lotus Construction Group was enlisted to draft conceptual drawings for the project and developed a scope of work that was included in the Request for Proposals (RFP) released in April 2024. The project will include the demolition and disposal of the existing appliances and fixtures, counters, cabinets, pony wall, and flooring. Following the demolition, Pineda General Construction, Inc. will install new walls and countertops per the new design. To complete the project, new flooring, electrical components, cabinets, fixtures, and cabinets will be installed. Lotus Construction Group will serve in a project management role to keep the construction project on schedule and to ensure adherence to the scope of work.

 

In April 2024, an RFP was sent directly to ten contractors and posted on the City website. Six potential contractors attended the mandatory pre-bid meeting held on Thursday, May 9, 2024. At the close of the bid period, no bids were received. Per the Public Contracting Code, if the identified bid process is followed and a responsive, responsible bidder is not identified, staff may directly negotiate with a contractor. Staff directly negotiated with OTL Builders, Inc. OTL Builders agreed to the scope of work and proposed a cost of $69,300. In September 2024, the City Council awarded contract to OTL Builders. Prior to signing the agreement, OTL Builders provided the City with a revised scope of work. OTL Builders did not agree to approximately half of the required work that was originally agreed upon and refused to sign the agreement.

 

In October 2024, an RFP was sent directly to six contractors and posted on the City website. Five potential contractors attended the mandatory pre-bid meeting held on November 7, 2024. At the close of the bid period, two bids were received for $109,595 and $127,700. Staff reviewed the proposals and determined Pineda General Construction, Inc. to be the lowest responsive, responsible bidder.

 

Staff recommends awarding a contract to Pineda General Construction, Inc. for the Blaisdell Community Center Kitchen Remodel Project. Pineda General Construction, Inc. has experience with similar projects. Staff contacted references for Pineda General Construction, Inc., which came back favorable. Additionally, staff recommends retaining Lotus Construction Group for project management services.

 

RELATIONSHIP TO CITY PLANNING DOCUMENTS

 

Staff has evaluated the agenda item in relationship to the City’s strategic and visioning documents and finds that it applies to the following City Planning Documents: Council Priorities, Sustainable City Plan, Economic Sustainability Plan, General Plan, and the 2024-26 Budget.

 

CEQA REVIEW

 

This item is not subject to environmental review under the California Environmental Quality Act (CEQA).

 

PUBLIC NOTICE PROCESS

 

The agenda and staff report for this item have been posted on the City website and distributed to interested parties. If you desire a copy, please contact the City Clerk’s Office.

 

Submitted by:                     Prepared by:

 

Jeremy Swan                     Cari Dillman

Community Services Director                     Community Services Manager