TO: ADAM PIRRIE, CITY MANAGER
FROM: JEREMY SWAN, COMMUNITY SERVICES DIRECTOR
DATE: NOVEMBER 24, 2026
Reviewed by:
City Manager: AP
SUBJECT:
Title
AWARD OF CONTRACT TO KRESSA LLC FOR THE PADUA HILLS THEATRE PERGOLA RENOVATION PROJECT (FUNDING SOURCE: GENERAL FUND)
Body
SUMMARY
The Padua Hills Theatre entryway pergola exhibits signs of wood rot and needs renovation. The proposed renovation project prioritizes the preservation and repair of the historic materials wherever feasible, rather than a complete removal and replacement. In October 2026, the City solicited bids for the Padua Hills Theatre Pergola Renovation Project. At the end of the bid period, four bids were received, ranging from $43,700 to $294,000. The lowest responsible, responsive bid was from Kressa LLC (Kressa).
The City had previously solicited proposals for this project, and in January 2026 awarded a contract to Pineda General Construction, Inc. (Pineda). However, due to the tight timeframe allowed for the work, Pineda was unable to complete the project within the contracted amount. After several months of negotiation, the City and Pineda mutually agreed to terminate the contract, allowing the City to rebid the project. To address this issue, the timeframe and working hours were adjusted in the Request for Proposals (RFP) before the RFP was reissued.
As established in Administrative Policy 10-25 (Reserve Policy), the City maintains a dedicated reserve fund for the purpose of addressing ongoing equipment and facility repair and/or maintenance, and/or the acquisition of needed amenities. Any use of these reserve funds is at the sole discretion of the City Council, and specific City Council action is required to authorize the use of any of the funds.
RECOMMENDATION
Recommended Action
Staff recommends the City Council award a contract to Kressa LLC in the amount of $50,420 for the Padua Hills Theatre Pergola Renovation Project, authorize a ten percent contingency in the amount of $5,042, for a total authorized amount not to exceed $55,462, and authorize the City Manager to execute the agreement.
Body
ALTERNATIVES TO RECOMMENDATION
In addition to the recommendation, there are the following alternatives:
A. Request additional information from staff.
B. Reject all bids and direct staff to rebid the project.
FINANCIAL REVIEW
The cost of the Padua Hills Theatre Pergola Renovation Project is $50,420. Staff recommends including a ten percent contingency of $5,042, for a total project cost of $55,462. Staff recommends utilizing the $56,595 previously appropriated from the Equipment and Facility Revolving Reserve for the project. The current appropriation from the Equipment and Facility Revolving Reserve is adequate to fund this new agreement and the remaining balance in the reserve is $2,027,577. Any unspent funds from this project will be returned to the Equipment and Facility Revolving Reserve.
The staff cost to prepare this report and administer this project is estimated at $2,750 and is included in the operating budget of the Community Services Department. The staff cost to prepare the Certificate of Appropriateness is estimated at $800 and is included in the operating budget of the Planning Division.
ANALYSIS
The pergola at the entrance to the Padua Hills Theatre is in need of repair and renovation. Rather than a complete removal and replacement, the proposed project prioritizes the preservation and repair of historic materials wherever feasible. Wood beams exhibiting localized rot will be retained and stabilized. Due to advanced deterioration, select beams, rafters, tongue-and-groove panels, and brick column caps will be replaced. The new materials will match the originals in material, design, dimension, texture, and appearance. The salvage and reuse of existing bricks will be prioritized, and replacement bricks, if required, will be compatible in size and character. Mortar caps will replicate the existing rounded profile to ensure visual continuity. Distinctive craftsmanship features, including the hand-chiseled or adze-scalloped detailing on crossbeams, will be replicated using hand tools to match the historic construction techniques.
Overall, the scope of work reflects a sensitive and minimally invasive approach that preserves the historic character and defining features of this National-Register-listed resource. Pursuant to Claremont Municipal Code Section 16.302.130, the Planning Division finds that the project meets all applicable criteria and issued a Certificate of Appropriateness for the project (Attachment).
In January 2026, the City entered into a contract with Pineda General Construction, Inc. (Pineda) in the amount of $51,450. In March 2026, City staff, Padua Hills Theatre staff, and Pineda met onsite for a pre-construction meeting. During the meeting, the timeframe for allowed days of work and work hours were discussed. The venue’s event calendar limited the available days and hours for the project, causing a significant increase in labor and mobilization costs. After several attempts to negotiate a reasonable timeframe and cost for increased services, the City and Pineda General Construction, Inc. mutually agreed to terminate the contract, allowing the City to revise and reissue the RFP.
In October 2026, a revised RFP was sent directly to three contractors and posted on the City’s website. Prior to release, the RFP was revised to include the allowed timeframe for work and working hours. Five potential contractors attended the mandatory pre-bid meeting held on Wednesday, October 21, 2026. At the end of the bid period, four bids were received, ranging from $43,700 to $294,000. All bids received are listed below:
|
Bidder |
Amount |
|
Kressa LLC |
$50,420 |
|
SAVI Construction |
$198,000 |
|
Leonida Builders, Inc. |
$294,000 |
|
Noble E & C |
$43,700 |
Although Kressa LLC is not the lowest bidder, staff determined Kressa to be the most responsive, responsible bidder. Kressa has been in business for longer and provided a superior list of current projects. Additionally, responses to staff’s check of Kressa’s references were all favorable regarding their workmanship, customer service, and completing projects within budget. Accordingly, staff recommends awarding a contract to Kressa LLC for the Padua Hills Theatre Pergola Renovation Project.
RELATIONSHIP TO CITY PLANNING DOCUMENTS
Staff has evaluated the agenda item in relationship to the City’s strategic and visioning documents and finds that it applies to the following City Planning Documents: Council Priorities, Sustainable City Plan, General Plan, and the 2026-28 Budget.
CEQA REVIEW
This item is not subject to environmental review under the California Environmental Quality Act (CEQA).
PUBLIC NOTICE PROCESS
The agenda and staff report for this item have been posted on the City website and distributed to interested parties. If you desire a copy, please contact the City Clerk’s Office.
Submitted by: Prepared by:
Jeremy Swan Cari Dillman
Community Services Director Community Services Manager
Attachment:
Certificate of Appropriateness