Title: AWARD OF CONTRACT TO ALL CITIES ENGINEERING, INC. AND TKE ENGINEERING, INC. FOR THE COLBY CIRCLE STORM DRAIN IMPROVEMENTS PROJECT, C.I.P. 2026-04 (FUNDING SOURCES: DRAINAGE FUND AND MEASURE W FUND)

TO:                     ADAM PIRRIE, CITY MANAGER

 

FROM:                     DAVID CRABTREE, INTERIM COMMUNITY DEVELOPMENT DIRECTOR

 

DATE:                     NOVEMBER 24, 2026

Reviewed by:

City Manager: AP

                     

SUBJECT:

 

Title

AWARD OF CONTRACT TO ALL CITIES ENGINEERING, INC. AND TKE ENGINEERING, INC. FOR THE COLBY CIRCLE STORM DRAIN IMPROVEMENTS PROJECT, C.I.P. 2026-04 (FUNDING SOURCES: DRAINAGE FUND AND MEASURE W FUND)

Body                     

 

SUMMARY

 

On September 30, 2026, the City of Claremont received ten bids for the Colby Circle Storm Drain Improvements Project, C.I.P. 2026-04. The lowest responsive and responsible bidder was All Cities Engineering, Inc., of Riverside, with a bid of $2,402,775.

 

The project includes the construction of a storm drain system supplemented with series of drywell systems. The roadway will be resurfaced following the completion of the project. This project was commissioned to address flooding during larger storm events observed in past years.

 

In addition to awarding the contract to All Cities Engineering, Inc., staff recommends retaining the consulting firm TKE Engineering, Inc. to provide inspection and construction management services to ensure the work is performed properly and according to plans and City Standards.

 

RECOMMENDATION

 

Recommended Action

Staff recommends the City Council:

A.                     Authorize the City Manager to execute an agreement with All Cities Engineering, Inc., in the amount of $2,402,775 and authorize a ten percent contingency in the amount of $240,278 for a total authorized amount not to exceed $2,643,053;

B.                     Authorize the City Manager to execute an agreement with TKE Engineering, Inc., in the amount not to exceed $145,278 for inspection and construction management;

C. Appropriate $1,099,330 in Measure W Funds to fully fund the project; and

D.                     Find this item is exempt from environmental review under the California Environmental Quality Act (CEQA).

Body

 

ALTERNATIVE TO RECOMMENDATION

 

In addition to the recommendation, there is the following alternative:

 

•                     Request additional information from staff.

 

FINANCIAL REVIEW

 

On September 30, 2026, the City received the following bids:

 

Bidder

City

Bid Amount (Alternative A)

Bid Amount  (Alternative B)

All Cities Engineering Inc.

Riverside

$2,449,075.00

$2,402,775.00

CP Construction Co. Inc.

Upland

$2,423,975.00

$2,436,175.00

CEM Construction Corp.

Montebello

$2,511,162.50

$2,467,662.50

US Builders

Placentia

$2,648,500.00

$2,598,400.00

MNR Construction Inc.

La Verne

$2,886,230.00

$2,688,830.00

Toro Enterprises Inc.

Temecula

$3,378,364.00

$3,371,554.00

Bubalo Construction Inc.

Baldwin Park

$3,573,475.00

$3,573,475.00

Kana Pipeline Inc.

Riverside

$3,588,120.00

$3,574,980.00

GRBCON

Baldwin Park

$3,711,296.00

$3,711,296.00

LA Engineering Inc.

Covina

$4,260,000.00

$4,542,000.00

 

This project requested bids for reinforced concrete pipe (RCP) (Alternative A) and HP Polypropylene Pipe (HP Pipe) (Alternative B). Both materials were listed for two separate bids, Alternative A and Alternative B. The bid specifications stated the award would be issued to the most responsive and responsible bidder for the low-bid amount regardless of the material. For this project, the HP Pipe option received the lowest amount from All Cities Engineering, Inc. in the amount of $2,402,775.

 

In addition to awarding the contract to All Cities Engineering, Inc., staff proposes to retain the consulting firm TKE Engineering, Inc. to provide inspections and construction management to ensure the work is performed properly, according to specifications and per City Standards.  This contract is recommended in the amount of $145,278.

 

The following funding sources will be used for this project:

 

Funding Source

Amount

Measure W Fund - Construction

$ 2,059,330

Drainage Fund - Construction

$ 343,445

Drainage Fund - Construction Contingency

$ 240,277

Drainage Fund - Construction Management and Inspection

$ 145,278

Total Project Costs:

$ 2,788,330

 

Partial funding for this project was included in the 2023-24 Capital Improvement Program (CIP) budget in the amount of $1,689,000. This amount is comprised of $960,000 in Measure W funds and $729,000 in Drainage funds. An additional $1,099,330 in Measure W funds is recommended to be appropriated to fully fund the project. Staff estimates that the Measure W fund will have an available fund balance of $1,367,871 in 2026-27 to fund this additional appropriation.

 

The staff cost to prepare this report is estimated at $1,112 and is included in the operating budget of Community Development Department.

 

ANALYSIS

 

On September 30, 2026, the City received ten bids from contractors ranging from $2,402,775 to $4,542,000. The apparent low Bidder, All Cities Engineering, Inc., (ACE), had a bid of $2,402,775.

 

This project will mitigate heavy stormwater runoff emanating from the Oxford Avenue and Colby Circle neighborhoods. In past years, staff observed increases in the frequency and intensity of storm events, resulting in increased stormwater runoff from Joat Park, the Claremont High School property, and other parcels in the near proximity to Colby Circle and Oxford Avenue neighborhoods.

 

The project will provide storm drain and drywell improvements along Colby Circle and Oxford Avenue. The drywells are positioned up-stream of certain catch basins to capture and infiltrate storm water prior to allowing storm water into the catch basins entering the storm drain system.  This strategy allows the City to reduce observed flooding during heavier storm events and to also infiltrate storm water, consistent with the City’s Municipal Separate Storm Sewer System (MS4) permit with the State of California.

 

Currently Colby Circle and Oxford Avenue are in satisfactory condition as far as pavement health is concerned. However, due to the amount of trenching required to install the storm drain mainline and necessary lateral lines connecting to the catch basins, the project includes resurfacing of the roadway once the storm drain improvements are complete. The roadway restoration will include the following:

 

•                     2-inch full-depth grind and conventional asphalt hot mix paving

•                     Replace all existing street striping

 

Once completed, the new storm drain system will connect to the existing storm drain system built with the Foothill Boulevard Master Plan Improvements Project (2020) along Foothill Boulevard.

 

RELATIONSHIP TO CITY PLANNING DOCUMENTS

 

Staff has evaluated the agenda item in relationship to the City’s strategic and visioning documents and finds that it applies to the following City Planning Documents: Council Priorities, Sustainable City Plan, General Plan and the 2026-28 Budget.

 

CEQA REVIEW

 

This item (Colby Circle Storm Drain Improvements Project) is not subject to environmental review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15060(c)(2) (the activity will not result in a direct or reasonably foreseeable indirect physical change in the environment) and Section 15060(c)(3) (the activity is not a “project” as defined in section 15378). CEQA Guidelines Section 15378(b)(2), (4), and (5) excludes “continuing administrative ... activities,” “government fiscal activities, which do not involve any commitment to any specific project which may result in a potentially significant physical impact on the environment,” and “administrative activities of governments that will not result in direct or indirect physical changes to the environment” from its definition of “project.”

 

Additionally, under CEQA Guidelines Section 15061(b)(3), it is covered by the general rule that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Award of this contract will not have a significant effect on the environment because the action will not result in or lead to a physical change in Claremont. Therefore, no additional environmental review is needed.

 

PUBLIC NOTICE PROCESS

 

The agenda and staff report for this item have been posted on the City website and distributed to interested parties. If you desire a copy, please contact the City Clerk’s Office.

 

Submitted by:                     Reviewed by:

 

David Crabtree                     Maria B. Tipping, P.E.

Interim Community Development Director                     City Engineer

 

                     Prepared by:

 

                     Vincent Ramos

                     Associate Engineer