Legislation Details

File #: 26-396    Version: 1 Name:
Type: Informational Report Status: Agenda Ready
File created: 10/26/2026 In control: City Council
On agenda: 11/24/2026 Final action:
Title: AWARD OF CONTRACT TO LCR EARTHWORK AND ENGINEERING CORPORATION AND AGREEMENT WITH EGIS GROUP FOR THE CLAREMONT BOULEVARD COMPLETE STREETS IMPROVEMENT PROJECT (FUNDING SOURCE: STATE GAS TAX)

TO:                     ADAM PIRRIE, CITY MANAGER

 

FROM:                     DAVID CRABTREE, INTERIM COMMUNITY DEVELOPMENT DIRECTOR

 

DATE:                     NOVEMBER 24, 2026

Reviewed by:

City Manager: AP

                     

SUBJECT:

 

Title

AWARD OF CONTRACT TO LCR EARTHWORK AND ENGINEERING CORPORATION AND AGREEMENT WITH EGIS GROUP FOR THE CLAREMONT BOULEVARD COMPLETE STREETS IMPROVEMENT PROJECT (FUNDING SOURCE: STATE GAS TAX)

Body                     

 

SUMMARY

 

On October 26, 2026, the City of Claremont received four bids for the Claremont Boulevard Complete Streets Improvement Project, C.I.P. 2026-02. The lowest responsive and responsible bidder was LCR Earthwork and Engineering Corporation, with a bid of $659,582.00 and $732,305.00 for Alternative A. Staff recommends awarding Alternative A, which will widen the existing sidewalk from five feet to six feet and replace the entire sidewalk corridor at the west side of Claremont Boulevard, from Ninth Street to Foothill Boulevard, providing a more cost-effective and comprehensive improvement within the approved project budget.

 

The Claremont Boulevard corridor between Sixth Street and Foothill Boulevard will be upgraded to a complete street layout to include traffic calming components such as pedestrian bulb outs, Class IV bike lanes, narrowed traffic lanes and more pedestrian friendly parkway/sidewalk options. As part of the approval of the Claremont University Consortium (CUC) East Campus project and Claremont McKenna College (CMC) Robert Day Sciences Center, CMC was required to install public improvements. The improvements required were limited to their property frontage, at the east side of Claremont Boulevard between Sixth Street and Foothill Boulevard, and the west side of Claremont Boulevard between Sixth Street and Ninth Street. The segment of Claremont Boulevard between Ninth Street and Foothill Boulevard is outside of CMC’s jurisdiction and was not included in CMC’s public improvement upgrades. Therefore, to provide a full Complete Streets corridor between Sixth Street and Foothill Boulevard, the City will be responsible for implementing complete street improvements that will be coordinated with the CMC project.

 

In addition to awarding the contract to LCR Earthwork and Engineering Corporation, staff recommends retaining the services of the consulting firm, Egis Group, to provide inspection and construction management services to ensure the work is performed in accordance with the approved plans and City Standards.

 

RECOMMENDATION

 

Recommended Action

Staff recommends the City Council:

A.                     Award a contract to LCR Earthwork and Engineering Corporation, authorize the City Manager to enter into an agreement with LCR Earthwork and Engineering Corporation in the amount of $732,305.00, and authorize a 10 percent contingency in the amount of $73,230.50, for a total authorized amount of $805,535.50 for the Claremont Boulevard Complete Streets Improvement Project, C.I.P. 2026-02;

B.                     Authorize the City Manager to execute an agreement with Egis Group in an amount not to exceed $108,450.00 for inspection and construction management services; and

C.                     Find the contract and the Claremont Boulevard Complete Streets Improvement Project exempt from the California Environmental Quality Act (CEQA).

Body

 

ALTERNATIVE TO RECOMMENDATION

 

In addition to the staff recommendation, there is the following alternative:

 

•                     Request additional information from staff.

 

FINANCIAL REVIEW

 

This contract complies with all City purchasing guidelines.  Bid and contract documents are available for review in the City Clerk's office.

 

Funding for this project is included in the 2026-2028 Capital Improvement Program (CIP) budget, under Complete Street Improvements - Claremont Boulevard. The State Gas Tax Fund will be utilized to fund this project.

 

The staff cost to prepare this report and administer this contract is estimated at $1,223 and is included in the operating budget of the Community Development Department.

 

ANALYSIS

 

On October 26, 2026, the City received the following bids:

 

Bidder

Location

Amount

Amount (Alternative A)

LCR Earthwork and Engineering Corp.

Jurupa Valley

$659,582.00

$732,305.00

Sequel Contractors, Inc.

Santa Fe Springs

$703,619.50

$865,933.00

Hardy and Harper, Inc.

Lake Forest

$736,614.00

$845,891.00

All American Asphalt

Corona

$861,378.10

$1,013,377.80

 

The apparent low bidder, LCR Earthwork and Engineering Corporation, had a bid of $659,582.00 and $732,305.00 for Alternative A according to their submittal. The bid documents included Alternative A, which provides for widening the existing five-foot sidewalk to six feet and the replacement of the entire length of sidewalk, rather than limiting improvements to segments requiring repair. Based on the available project budget, awarding Alternative A is the most cost-effective option, as it will facilitate the replacement of the entire sidewalk corridor on the west side of Claremont Boulevard, from Ninth Street to Foothill Boulevard.

 

In addition to awarding the contract to LCR Earthwork and Engineering Corporation, staff recommends retaining the services of the consulting firm, Egis Group, to provide inspection and construction management services to ensure the work is performed in accordance with the approved plans and City Standards. The contract is recommended in an amount not to exceed $108,405.00.

 

Background

 

In December 2016, the then Claremont University Consortium (CUC), requested that the City Council approve a map subdividing thirty acres in the City of Claremont for the future implementation of the Colleges’ East Campus project. The City Council approved PM 70243 for the subdivision of these thirty acres, on the east side of Claremont Boulevard from Arrow Route and Foothill Boulevard. The East Campus site is only partially located in the City of Claremont, with thirty acres in the city and 45 acres in the City of Upland.

 

As part of this approval, CUC was required to complete public improvements along the east side of Claremont Boulevard between Sixth Street and Foothill Boulevard. Since its approval, CMC has acquired the East Campus project and is now responsible for the public improvement requirements associated with this project.

 

In addition, CMC was approved for the construction of the Robert Day Sciences Center, located at the southwest corner of Ninth Street and Claremont Boulevard. Similarly, CMC was required to provide public improvements along the project frontage and extend to Sixth Street to be consistent with the east side requirements.

 

Therefore, the east side of Claremont Boulevard between Sixth Street and Foothill Boulevard and the west side of Claremont Boulevard between Sixth Street and Ninth Street will be upgraded by CMC to a complete street with traffic calming components such as pedestrian bulb outs, Class IV bike lanes, narrowed traffic lanes, and more pedestrian friendly sidewalk options, that include a new bus stop with amenities and accessibility components.

 

The west segment of Claremont Boulevard between Ninth Street and Foothill Boulevard is outside of CMC’s jurisdiction and was not included in CMC’s required public improvements upgrades. Therefore, to provide a full Complete Streets corridor between Sixth Street and Foothill Boulevard, the City will be responsible for implementing complete street improvements to be coordinated with the CMC project. Timing and weather permitting, the goal is to construct the northwest portion of Claremont Boulevard (the City’s portion) in coordination with the remainder of the CMC construction in hopes of limiting the disruption to the community.

 

Scope of Work

 

The project scope of work includes the following improvements:

1.                     Class IV bike lanes

2.                     Green Bike Lanes where appropriate

3.                     Narrowed traffic lanes

4.                     Americans with Disabilities Act (ADA) Improvements

a.                     Sidewalk replacement

b.                     Bus Stop with Amenities

5.                     Grind and repaving

6.                     Streetlight mast arm replacement

 

RELATIONSHIP TO CITY PLANNING DOCUMENTS

 

Staff has evaluated the agenda item in relationship to the City’s strategic and visioning documents and finds that it applies to the following City Planning Documents: Council Priorities, Sustainable City Plan, General Plan, and the 2026-28 Budget.

 

CEQA REVIEW

 

The Claremont Boulevard Complete Streets Improvement Project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA guidelines. The Class 1 exemption allows for the maintenance and repair of topographical features with negligible or no expansion. The project will perform maintenance work on existing infrastructure (asphalt, curb and gutter). The work being performed is within existing right-of-way areas and will not expand the capacity of the roadway infrastructure.

 

COMMISSION REVIEW

 

The Claremont Boulevard Complete Street project (both CMC and City segments) has been presented to the Traffic and Transportation Commission with subsequent updates throughout the corridor improvements process. This project has been well received and supported by the Commission.

 

PUBLIC NOTICE PROCESS

 

The agenda and staff report for this item have been posted on the City website and distributed to interested parties. If you desire a copy, please contact the City Clerk’s Office.

 

Submitted by:                     Reviewed by:

 

David Crabtree                     Maria Tipping, P.E.

Interim Community Development Director                     City Engineer

 

                     Prepared by:

 

                     Jasmin Hurtado, P.E.

                     Associate Engineer